Price Adjustment in a Romanian Supply Agreement: Review Before Accepting an Increase

Romanian supply contracts · Price increases · Buyer-side advice

Your Romanian supplier has announced a new price for goods or services that your business already buys under a supply agreement.

Before approving the increase, check which orders are binding, whether the contract actually permits adjustment, and what happens to delivery if the parties disagree.

In brief: A supplier’s higher costs do not automatically change an agreed price under Romanian law.

An agreed indexation formula, a valid amendment, a fresh order at a new price or an applicable legal rule may produce a different result.

The buyer’s response should address the exact contract and order position, preserve supply and record what is accepted or disputed.

This guide is for foreign companies buying from a Romanian supplier, including manufacturers, distributors and groups managing procurement from abroad.

It concerns private commercial agreements; public procurement, regulated tariffs and consumer purchases may follow different rules.

The Romanian Civil Code analysis below applies where Romanian domestic law governs the relevant issue. For an international sale of goods, first assess whether the CISG applies: it may govern contract formation and the parties’ sales obligations instead of the corresponding domestic rules.

Can a Romanian supplier raise the price during an existing contract?

The answer begins with the signed agreement and the particular purchase order, not with the supplier’s announcement.

Under Article 1270 of the Romanian Civil Code, a valid contract binds its parties and is amended or ended by their agreement or on a ground authorised by law.

For an arrangement legally classified as a supply contract, Article 1768(1) provides that the beneficiary owes the price specified by contract or law.

These rules do not make every price fixed forever: the parties may have agreed a mechanism that changes it, or they may agree a new price for future orders.

Equally, a supplier’s email saying that raw materials, wages or transport have become more expensive does not, by itself, establish a contractual entitlement to invoice a higher amount for an already binding order.

A price increase charged by the supplier’s own subcontractor does not, by itself, establish a right to increase the buyer’s agreed price. Check any contractual pass-through or price-adjustment mechanism and any applicable legal grounds separately.

Start with the complete document set: master supply agreement, signed amendments, price schedule, ordering terms, accepted purchase orders, forecasts and any agreed hierarchy between them.

The title of the document is not decisive. Article 1766 describes a supply contract for goods to be delivered, or services to be performed, at one or more later dates or continuously; Article 1771 provides for supplementary application of sale rules where appropriate.

A single delivery, a long-term framework and a series of separately accepted orders can create different price commitments even between the same parties.

Which price-change route does the supplier invoke?

Match the request to the documents before responding.

Contract formula

An index, exchange-rate mechanism or cost trigger may adjust price if its conditions and notice requirements are met.

New agreement

The parties may negotiate a prospective amendment or accept a future order at a revised price.

Hardship claim

Exceptional circumstances may support a request for judicial adaptation under Article 1271, subject to strict conditions.

These routes require separate analysis; a notice invoking one route does not establish the others.

What should you check in a price adjustment clause?

Read the whole clause, including the schedules and the terms governing orders, rather than the sentence allowing a price review.

Does it permit an automatic calculation, a proposal that requires consent, or only a right to reopen negotiations?

Identify the trigger, index or cost category, reference period, formula, currency, cap, minimum threshold, frequency and effective date.

Check who supplies the supporting data, whether the supplier must show actual cost movement, and whether the calculation can be tested against an independent published index.

A clause referring to an annual inflation index does not necessarily support a mid-year change tied to a different input cost.

A fuel surcharge applicable to transport may not change the underlying unit price of goods unless the contract says it does.

Notice provisions matter: an increase that requires 60 days’ written notice should be tested against the date, channel and content of the supplier’s actual communication.

Also check whether the adjustment reaches orders already accepted, only orders placed after a stated date, or a defined batch of undelivered goods.

Where the contract lets the buyer terminate or reduce volumes after a proposed increase, map that choice against minimum-purchase obligations, exclusivity and outstanding orders.

Supplier standard terms attached to a quotation may conflict with the negotiated master agreement. Determine which terms were incorporated and which document prevails before treating the new quote as an amendment.

Where Romanian domestic law applies, Article 1203 requires express written acceptance for specified unusual standard clauses favouring their proponent, including a right to suspend performance or unilaterally terminate the contract. Whether a particular price-adjustment mechanism also requires separate express acceptance depends on its drafting and effect; do not assume every such clause falls within Article 1203 merely because it may increase the price.

For a wider approach to these conflicts, see our Romanian contract review checklist and our guide to negotiating a supplier framework agreement.

Do accepted orders keep the old price?

There is no reliable answer without examining how orders become binding under the agreement.

An accepted purchase order with a stated unit price and delivery date may already be a contractual commitment, but the master agreement may expressly reserve a valid adjustment mechanism for undelivered quantities.

Whether a purchase order forms a separate contract or operates under a framework agreement’s pricing mechanism depends on the parties’ contractual structure and the order-acceptance process.

A forecast may be non-binding, partly binding inside a frozen window, or subject to a separate acceptance step.

An unsigned quotation for future purchases is different from a supplier’s unilateral attempt to reprice goods already ordered under an enforceable commitment.

Prepare an order-by-order schedule showing the original price, order date, acceptance evidence, quantity, planned delivery, invoicing status and the supplier’s proposed new price.

This prevents a negotiation over next quarter’s orders from accidentally becoming an argument about an accepted order due next week.

Look closely at portal approvals, electronic order acknowledgements and the parties’ established exchange of documents.

Under Romanian domestic contract-formation rules, Article 1196(2) provides that silence or inaction does not normally amount to acceptance, unless a different result follows from the law, the parties’ agreement, established practices, trade usages or other circumstances.

Payment of a revised invoice, a new purchase order or continued ordering after a clear change notice can carry evidentiary consequences; whether it amounts to acceptance depends on the communications and governing contract.

If a delivery is operationally essential, a written interim arrangement can specify which quantities move now, at what price, and whether either party reserves its position about disputed amounts.

Does inflation or a cost shock give the supplier a hardship claim?

Article 1271 of the Romanian Civil Code on hardship (impreviziune) starts from the rule that parties must perform even if performance becomes more onerous because costs increase or the value received decreases.

A court may adapt or terminate the contract only where performance has become excessively onerous because of an exceptional change of circumstances that would make it manifestly unjust to hold the debtor to its obligation, and the further statutory conditions are met.

Adaptation is intended to distribute equitably between the parties the losses and benefits resulting from that change; a court determines the timing and conditions of termination.

The statutory route requires, among other things, that the change occurred after the contract was concluded; that neither the change nor its extent was, or could reasonably have been, taken into account by the debtor at that time; that the debtor neither assumed nor could reasonably be considered to have assumed the risk of the change; and that the debtor attempted, within a reasonable time and in good faith, to negotiate a reasonable and equitable adaptation of the contract.

Whether those conditions are met depends on the agreement, the risk allocation, timing, evidence of cost movement and the actual effect on performance.

A commercial request to renegotiate is not the same as a successful hardship claim, and invoking hardship does not itself rewrite the invoice price.

Where the CISG governs an international goods sale, the relationship between its Article 79 regime and any proposed reliance on domestic hardship rules requires a separate analysis. Do not assume that Article 1271 applies to the same issue.

Ask the supplier to explain the affected inputs, when the change occurred, how it affects this contract, what risk was already allocated and what alternative adjustment it proposes.

A force-majeure clause or a delivery disruption requires its own analysis. Higher cost alone should not be described as automatic impossibility to perform.

Our guide to ending a supplier contract in Romania addresses the separate question of whether an exit route exists if the relationship cannot continue.

What if the supplier cites a new law or regulated price?

Article 1768 of the Civil Code has a narrower, specific rule for a change in the legal regulation of a price or pricing mechanism during a supply contract.

Under paragraph (2), the original contractual price or mechanism continues between the parties unless the new law expressly provides otherwise.

Under paragraph (3), if the law expressly applies its new price or method to contracts already in progress, either party may unilaterally terminate the contract (denunțare unilaterală) within 30 days of the law’s entry into force; the contractual price applies during that period.

This is not a general 30-day cancellation right whenever a supplier’s commercial costs rise.

If a supplier invokes a tax, tariff or regulatory change, obtain the exact enactment, effective date and explanation of how it applies to this contract and to the particular goods or services.

Check the specific enactment for any special or derogating provisions.

Do not confuse a tax amount that must lawfully appear on an invoice with a contractual right to increase a net commercial unit price.

How should the buyer respond without disrupting supply?

First acknowledge the notice without approving an unverified price, then request the contractual basis, calculation, supporting evidence and list of affected orders.

Record the buyer’s current position on accepted orders and identify the date by which a business decision is needed to keep deliveries moving.

Do not assume that a general reservation of rights cures contradictory conduct. Procurement, finance and the receiving warehouse should work from the same order schedule and agreed response.

Consider a limited negotiation: a temporary surcharge, staged increase, index-linked revision, volume adjustment, shorter fixed-price period or an agreed right to source elsewhere.

Define what happens when the underlying input cost falls. A one-way adjustment can have a different economic effect from a mechanism that moves both up and down.

If the supplier threatens to suspend deliveries, examine the actual delivery obligations, any contractual suspension right, notice requirements, disputed and undisputed invoices, and the consequences of a stop for each party.

Where Romanian domestic law applies, Article 1556 may permit a proportionate refusal to perform when reciprocal obligations are due and the other party neither performs nor offers performance, subject to the applicable order of performance and good-faith limits.

In particular, refusal may be contrary to good faith where the other party’s unperformed obligation is of minor importance in the circumstances.

A disagreement over a proposed price increase does not, by itself, establish the conditions for withholding performance.

A right to insist on performance of existing binding orders is not necessarily a right to require the supplier to accept new orders or continue the relationship indefinitely.

Likewise, withholding payment or rejecting all shipments without assessing the contract may create a second dispute. The buyer’s response should be proportionate to the position it can substantiate.

Any amendment should identify affected products, price table, start date, status of existing orders, duration, review trigger, governing terms and signatories.

For a continuing relationship, a short written amendment may be more useful than an exchange of emails whose legal effect later becomes contested.

Does a foreign-law clause change the analysis?

It may. A Romanian supplier and foreign buyer do not automatically have a Romanian-law contract simply because manufacturing or delivery takes place in Romania.

Regulation (EC) No 593/2008 (Rome I) addresses the law applicable to contractual obligations, including party choice under Article 3 and the rules used where no effective choice is made under Article 4.

In the absence of an effective choice, Article 4 generally connects a sale of goods to the seller’s habitual residence and a contract for services to the service provider’s habitual residence, subject to its other classification rules and exceptions, including the distinct rule for distribution agreements.

Check the governing-law and dispute clauses in the master agreement, incorporated terms and orders before applying a Civil Code rule to the price dispute.

Place of delivery, invoice currency and the supplier’s Romanian registration do not by themselves settle the applicable-law question.

For a cross-border sale of goods, also check whether the UN Convention on Contracts for the International Sale of Goods (CISG) applies and whether the parties have excluded it; Romania is a contracting state, but the convention’s scope must be assessed for the particular transaction.

For a qualifying international sale, choosing Romanian law does not, by itself, exclude the CISG, which forms part of the applicable legal framework unless the parties have effectively excluded it under Article 6.

The CISG does not govern a standalone services contract. Mixed goods-and-services arrangements require a separate scope assessment, including the preponderant-services test in Article 3(2).

Where another law governs, obtain advice on that law while Romanian counsel assesses any relevant Romanian performance, evidence or enforcement issues within the agreed engagement scope.

What should you send for a focused legal review?

DocumentQuestion it helps answer
Master agreement, amendments and standard termsWho can change the price, by which mechanism, and what terms prevail?
Price lists, index data and supplier noticeDoes the proposed calculation follow the contract and timing requirements?
Purchase orders, acknowledgements and forecastsWhich quantities and prices are already binding?
Invoices, delivery records and correspondenceWhat has been performed, paid, disputed or potentially accepted?
Internal supply and margin assessmentWhich interim deal or alternative source is commercially workable?

A focused instruction to counsel can ask for an order map, the strongest contractual position, the risks of rejection or interim payment, and a proposed response or amendment.

Atrium can review the Romanian-law position, draft a supplier response and negotiate revised terms for the affected business relationship, subject to conflict checks and agreed engagement scope.

No particular price concession, continued delivery or dispute outcome can be guaranteed.

Request a Romanian supply price review

Frequently asked questions

Can a Romanian supplier increase prices just because its costs rose?

Generally, higher costs alone do not amend an agreed price. Review the contract’s adjustment clause, the status of each order, any later agreement and any applicable legal route.

Does a price increase notice apply to purchase orders already accepted?

That depends on how the orders became binding and whether the governing terms validly permit an adjustment to them. Separate accepted orders from forecasts and future orders before responding.

Can the supplier invoke hardship under Romanian law?

Article 1271 permits judicial adaptation or termination where an exceptional change makes performance excessively onerous and holding the debtor to its obligation would be manifestly unjust, provided that further statutory conditions are met, including the foreseeability, risk-allocation and good-faith renegotiation requirements. A supplier’s hardship notice does not itself set a new price.

Can we reject the increase and still require delivery?

Possibly, if a binding order remains at the agreed price and no valid adjustment or suspension right applies. Check the contract, order evidence, payment position and practical risk before issuing a demand or withholding payment.

Does Romanian law give either party 30 days to cancel after a price rise?

No general 30-day right applies to ordinary commercial price rises. Article 1768(3) concerns the specific situation in which a new law expressly applies a new price or pricing method to ongoing supply contracts.

What if the contract is governed by foreign law?

Determine the applicable law under the contract and relevant conflict-of-law rules before relying on Romanian Civil Code remedies. For an international sale of goods, separately assess whether the CISG applies and whether it has been effectively excluded. A choice of national law does not, by itself, necessarily exclude the Convention.

Related guidance

Legal information and scope

This article is general information about commercial supply arrangements and is not legal or tax advice for a particular transaction.

The outcome depends on the full contract, applicable law, facts and documents. Contacting the firm does not create a lawyer-client relationship or preserve a contractual or legal deadline.

AI-assisted content.

Geometric maze illustrating contractual risk assessment during a contract review in Romania

Contract Review in Romania: 12 Clauses to Check

Which contract clauses should a business check before signing?

A Romanian business contract should clearly allocate performance, payment, liability, intellectual-property, data and exit risks. These 12 clauses are the practical starting point for a legal and commercial review.

Contract review in Romania should test more than whether an agreement is formally valid. Before signing, a business should understand what it must deliver, when it will be paid, which losses it may bear, how intellectual property and data may be used, and how the relationship can end.

Commercial contracts are often negotiated under pressure. A supplier is ready to begin, a customer wants the final draft immediately, or a foreign group needs its Romanian operation running without delay. That is precisely when unclear wording, inconsistent annexes and borrowed template clauses are most likely to pass unnoticed. Companies entering the market should connect the contract with the wider steps required to start and operate a business in Romania.

Interconnected architectural structure illustrating how contract clauses work together in a Romanian contract review
A well-structured contract depends on interconnected clauses that allocate obligations, remedies and commercial risks consistently.

Under the Romanian Civil Code, a validly concluded contract is binding on the parties, and contractual negotiations and performance are governed by good faith. A useful review therefore connects the legal wording with the operational deal. It identifies which party controls each risk, whether the agreed remedy can work in practice, and what evidence will be needed if performance is disputed.

The following 12 clauses form a practical checklist for Romanian companies and foreign businesses entering agreements governed by Romanian law or involving a Romanian counterparty.

Parties, capacity and signing authority

The contract should identify the correct legal entities, not merely the brand names used in negotiations. For a Romanian company, check its registered name, registered office, Trade Registry number, fiscal identification code and representative. If a group is involved, establish which entity receives the services, issues invoices, owns the relevant assets and assumes liability.

Signing authority should be verified against the company’s constitutional documents, Trade Registry information, corporate approvals or a power of attorney. A signature block describing someone as a “manager” does not itself resolve whether that person may bind the company for the relevant transaction. The representation rules should be checked against the company’s current Romanian articles of incorporation and the registered powers of its administrators.

The internal authority analysis also matters for potential Romanian company director liability, particularly where a director signs outside approved limits or fails to document a material commercial decision.

Check before signingConfirm the contracting entity, the signatory’s authority, any required corporate approval, the position of affiliates and whether subcontracting or assignment to another group company is permitted.

Scope, deliverables and acceptance

The scope clause should describe the goods or services, specifications, quantities, locations, deadlines, dependencies and exclusions. For project work, it should also establish milestones, acceptance tests, correction periods and a change-control procedure.

Review the main agreement together with proposals, statements of work, order forms and technical annexes. If they conflict, an order-of-precedence clause should determine which document controls. Acceptance by silence should also be tested carefully: specify when the review period begins, what constitutes a valid rejection and what happens when defects are minor. Providers using standard customer documentation should also verify the applicable service contract requirements in Romania.

Common riskThe commercial proposal promises one result, the technical annex describes another and the general conditions allow the supplier to treat delivery as accepted before meaningful testing has taken place.

Price, VAT, invoicing and payment

A complete payment clause states the price or calculation method, currency, VAT treatment, invoicing trigger, payment deadline, supporting documents, bank charges and the procedure for disputing an invoice. It should also explain whether the customer may withhold, deduct or set off amounts and whether the supplier may suspend performance for non-payment.

For B2B transactions, Law no. 72/2013 on late payment contains mandatory protections. Article 5(1) establishes a general 60-calendar-day limit for contractual payment terms between professionals. By exception, the parties may agree a longer payment term, provided that the clause is not abusive under Article 12. A term exceeding 60 days is therefore not automatically invalid, but it should be assessed carefully for gross unfairness to the creditor in light of the statutory criteria and the circumstances of the transaction. Where the applicable conditions are met, late payment can trigger statutory penalty interest and the fixed EUR 40 recovery compensation.

For the calculation rules and available remedies, see our guide to late-payment interest and penalties in Romania.

Term, renewal and minimum commitments

The agreement should state its effective date, initial duration and whether it renews automatically. An automatic renewal clause is not necessarily problematic, but the notice window, notice method and effect of a missed deadline must be clear.

Check minimum purchase commitments, exclusivity, take-or-pay obligations and price changes that continue into a renewal term. Add internal calendar reminders for any deadline that determines whether the company remains bound for another year or loses a renegotiation opportunity.

Check before signingIdentify the earliest exit date, the last date for a non-renewal notice and every financial or operational commitment that survives renewal.

Termination, cure periods and exit assistance

The termination clause should distinguish between serious breach, remediable breach, insolvency-related events, prolonged force majeure and termination for convenience. It should specify whether prior notice is required, how long the defaulting party has to cure, and whether termination operates through a contractual mechanism or requires another legal step.

The Romanian Civil Code regulates remedies for non-performance, including termination under Article 1549 and the related provisions. The contract should not merely say that a party “may terminate immediately”. It should align the grounds, notice mechanics and agreed effects with the type of contract and the intended remedy.

Exit provisions matter just as much as the termination trigger. Address final invoices, transition assistance, return of equipment and documents, data export, deletion, continued licences and the clauses that survive termination.

Penalty clauses and late-payment interest

A penalty clause fixes in advance the consequence of non-performance, defective performance or delay. Under Article 1538 of the Romanian Civil Code, its drafting should identify the protected obligation, the triggering event and the calculation method. The agreement should also state whether a penalty is daily or fixed, whether it is capped and how it interacts with damages and other remedies.

Article 1541 permits a court to reduce a penalty in the statutory circumstances, including where it is manifestly excessive in relation to the loss that the parties could have foreseen when concluding the contract. A high percentage is therefore not a substitute for careful drafting.

Common riskA daily penalty has no cap, applies to several overlapping obligations and continues after termination, creating exposure far beyond the economic value of the contract.

Liability caps, exclusions and indemnities

Liability provisions should allocate risk in proportion to the contract’s value, the parties’ control and the available insurance. Review the general cap, any separate or higher caps, excluded categories of loss, claims procedures and responsibility for employees, affiliates and subcontractors.

Do not assume that an indemnity is a familiar standard clause. It should identify the covered events, third-party claims, control of the defence, settlement authority, notification duties and mitigation. Check whether the limitation of liability applies to the indemnity or whether it creates uncapped exposure.

Any exclusion or limitation must also be tested against mandatory law and the nature of the conduct involved. A clause should not be described as protecting a party against every possible form of unlawful conduct. Where the agreement supports a wider investment or group operation, the liability wording should be reviewed together with the company’s corporate and commercial governance arrangements.

Warranties, regulatory compliance and audit rights

Warranties should be specific to the transaction. Depending on the contract, they may cover conformity with specifications, professional licences, legal compliance, authority, sanctions, anti-bribery, tax status, employment practices, product safety or the absence of third-party rights.

The review should also establish the remedy for an inaccurate warranty. Possible outcomes include correction, replacement, a price adjustment, indemnification or termination. An audit right should define scope, frequency, confidentiality, cost allocation and the treatment of identified non-compliance.

Drafting pointA broad promise to comply with “all applicable laws” may be necessary, but it does not replace transaction-specific duties, evidence requirements and an agreed remediation process.

Force majeure, hardship and change in law

Force majeure and hardship solve different problems. Force majeure concerns an external, unforeseeable, absolutely invincible and unavoidable event under the Civil Code framework. Hardship under Article 1271 addresses an exceptional change that makes performance excessively onerous, subject to the statutory conditions and the allocation of contractual risk.

The clause should define notice, evidence, mitigation, suspension, continued payment obligations and the point at which prolonged disruption permits termination. For regulated or long-term projects, add a change-in-law mechanism explaining who bears new compliance costs and whether price or timing may be adjusted.

Check before signingDo not treat every supplier delay, price increase, staff shortage or market change as force majeure. The clause should distinguish ordinary commercial risk from qualifying events.

Confidentiality and intellectual property

A confidentiality clause should define protected information, permitted use, internal access, legally required disclosures, security standards, duration and return or destruction. Trade-secret protection also depends on practical steps, so access controls and marking procedures should match the contractual wording. A standalone non-disclosure agreement in Romania may be appropriate before sensitive negotiations begin.

For intellectual property, distinguish pre-existing materials from deliverables created under the contract. State whether rights are assigned or licensed and address territory, duration, field of use, sublicensing, modifications, source materials and third-party components.

Romanian Law no. 8/1996 on copyright requires an assignment of economic copyright to specify the transferred rights and, for each, the modes of use, duration, extent and remuneration. A generic sentence stating that the customer “owns everything” may therefore be insufficient for the intended result. Businesses acquiring or licensing valuable assets can obtain a separate review from intellectual property lawyers in Romania.

For ownership arrangements between founders and shareholders, see our guide to shareholder agreements in Romania.

Personal data, security and digital services

If the agreement involves personal data, identify whether each party acts as controller, processor, joint controller or independent controller. When a supplier processes personal data on behalf of a controller, Article 28 of the General Data Protection Regulation requires a contract containing specified safeguards. Our GDPR compliance checklist for Romanian companies explains the wider governance controls that should support those clauses.

Review processing instructions, confidentiality, security measures, subprocessors, assistance with data-subject requests, breach notification, international transfers, audit rights and return or deletion. The commercial agreement and data processing agreement should not contain inconsistent liability, notice or termination rules. More complex vendor arrangements may require assistance from GDPR and data protection lawyers in Romania.

For SaaS and other digital services, also check availability commitments, backups, recovery objectives, vulnerability management, incident cooperation, data portability and access after termination. Technology businesses should align these provisions with their wider technology and digital law obligations and, where relevant, obtain a focused IT and software contract review.

Governing law, jurisdiction and notices

In cross-border contracts, governing law and forum are separate questions. The Rome I Regulation generally allows the parties to choose the law governing their contractual obligations, subject to its safeguards and mandatory rules. The Brussels I bis Regulation governs jurisdiction and the recognition and enforcement of judgments in relevant EU civil and commercial matters.

Consider whether the selected court or arbitral tribunal is proportionate to the likely dispute, where evidence and assets are located, the language and cost of proceedings, and whether an eventual judgment or award can be enforced efficiently.

The notice clause should identify valid addresses, permitted delivery methods, deemed receipt and the process for updating contact details. A termination or claim notice sent to the commercial contact may fail if the contract requires delivery to a different address or by a specific method. Where non-payment is already a concern, the agreement should be tested against the available legal recovery options for unpaid invoices in Romania.

Contract review in Romania: risk map

Contract areaQuestion to answerRisk if unclear
AuthorityIs the correct entity bound by an authorised person?Enforceability, approval and group-liability disputes.
PerformanceWhat exactly must be delivered, tested and accepted?Disputes over completion, defects and payment.
PaymentWhen is money due and what follows from delay?Cash-flow loss, penalties and invoice disputes.
ExitHow can the relationship end and what survives?Lock-in, service interruption and lost data.
LiabilityWhich losses are covered, capped or excluded?Exposure disproportionate to contract value.
IP and dataWho owns or may use assets, information and data?Loss of rights, GDPR exposure and operational dependency.
DisputesWhich law, forum and notice rules apply?Unexpected cost and difficult enforcement.

A practical pre-signing review process

Confirm the commercial dealRecord the intended result, price, timeline and points already agreed before editing legal language.
Read every contract documentReview the agreement, annexes, order forms, proposals, policies and incorporated online terms together.
Rank the risksSeparate legal defects, high-value commercial exposure, operational ambiguity and points that are negotiable preferences.
Propose usable wordingConvert each material issue into a replacement clause, tracked change or clear negotiation question.
Check signing and evidenceConfirm authority, approvals, signature method, final attachments and preservation of the executed version.
Calendar post-signing dutiesTrack notices, renewals, price reviews, certificates, audits and delivery or payment milestones.

Need a Romanian contract reviewed before signing?

Atrium Romanian Lawyers assists Romanian and foreign businesses with contract review, drafting and negotiation. The review can be delivered as tracked changes, replacement clauses, a consolidated draft or a practical risk report adapted to your position in the transaction.

Frequently asked questions

Is a business contract written in English valid in Romania?

Romanian companies can generally conclude commercial contracts in English. The transaction may nevertheless require Romanian-language documents or translations for authorities, courts, employees, consumers, notaries or regulated formalities. The governing-language clause should state which version prevails if the contract is bilingual.

Can a foreign-law contract be used with a Romanian company?

Potentially, yes. In a cross-border contract, the parties may often choose the governing law, but the Rome I framework, mandatory rules, the place of performance and the practical enforcement route must be considered. Choosing foreign law does not automatically remove every Romanian mandatory provision relevant to the transaction.

Are contractual penalties enforceable in Romania?

Romanian law recognises penalty clauses, but the obligation, trigger and calculation must be clear. Article 1541 of the Civil Code permits judicial reduction in the statutory circumstances, including a penalty that is manifestly excessive compared with the foreseeable loss at contract formation.

When should contract review in Romania take place?

Ideally before signing and before the commercial position becomes difficult to change. A new review is also appropriate before renewal, when the scope or price changes, when a party proposes an amendment, or when performance problems and a possible dispute emerge.

What should a foreign company send to the reviewing lawyer?

Send the complete draft and annexes, the commercial proposal, your role in the transaction, the applicable deadline, the principal business concerns and any terms already agreed. Identifying whether you are the customer, supplier, licensor, employer, investor or distributor changes the risk analysis.

Disclaimer: This article provides general legal information and does not constitute legal, tax or commercial advice. Contractual rights and risks depend on the complete document, the transaction, the parties, mandatory rules and the relevant facts.

AI Notice: AI-assisted content, reviewed and approved by a qualified Romanian lawyer.